Stiesdal Hydrogen Plant in operation in Glansager Denmark at a PtX plant site.

The 3.1 MW HydroGen Electrolyser

Each 3.1 MW electrolyzer is a self-contained unit consisting of four European-made main modules designed exclusively for outdoor installation. By eliminating the need for complex industrial buildings, the system simplifies site preparation and scales linearly.

Scope of supply

  • Pressurized Alkaline stack including temperature control
  • Power supply (PSU) module with active rectifier based on IGBTs and supply for auxiliaries
  • UPS-backed unit control system including dedicated safety PLC
  • Auxiliary module including pumps, and heat exchanger
  • Cooling systems for stack, PSU, and gas
  • Pressure vessel including vents, gas & water separation, and high performance diffusion filter
  • Process and electrical interconnections within and between modules

System price

  • EUR 2,100,000 – 2,250,000

24 months warranty period, Stiesdal Hydrogen standard terms, conditional on volume and delivery period.

Two 3.1 MW HydroGen Electrolysers at a customer site. Each system unit is built from standardised and modularised components.
The pressurised tanks enable the stacks to supply hydrogen at pressures up to 35 bar without the need for compression.
The electrode stack system is a novel design that allows the full stack to be easily handled in and out of the electrolyser pressure vessel.
The main system component, the pressurised tank containing the electrode stack, being delivered to a customer site.
The power and process modules are standardised components supplied by established industrial partners.
Three 3.1 MW units are operating at the Glansager site in Denmark, demonstrating a practical pathway towards large-scale, cost-effective green hydrogen production.